Completed Projects

The following are some of our completed projects:

49er Stadium Prep Make Ready Work
Client:  City of Santa Clara DPW
Description of Work: Site prep for new stadium, including earthwork, finegrade rock and pave, sewer, water and storm drains.
Value:  $10,422,000.00
Work Completed:

 

Graton Rancheria Casino
Client:  Perini Building Company
Description of Work: Site work including grading, paving, underground and concrete
Value:  $16,639868
Work Completed:

 

Highway 116 Schellville
Client:  Caltrans
Description of Work: Creek Realignment and landscaping
Value:  $1,907,763
Work Completed:

 

2013 Pavement Preservation Program
Client:  County of Sonoma
Description of Work: Full depth Reclamation and asphalt overlay of County roads
Value:  $6,414,070
Work Completed:

 

2013 Pavement Preservation Program
Client:  County of Sonoma
Description of Work: Full depth Reclamation and asphalt overlay of County roads
Value:  $6,414,070
Work Completed:

 

2013 Streeetscape Project
Client:  City of Healdsburg
Description of Work: Streetscape of downtown Healdsburg
Value:  $1,331,365
Work Completed:

 

El Charro Specific Plan Infrastructure Project Phase 1- Livermore
Client:  City of Livermore
Description of Work: Site development for new roads and water diversion areas, including earthwork, finegrade rock
Value:  $9,350,000
Work Completed:

 

#04-0A1844 – HWY 101 at Pepper Road- Petaluma
Client:  CalTrans
Description of Work: Widen Roadway from 4 to 6 lanes and creek bridge.
Value:  $10,759,347.00
Work Completed:

 

Castro Valley Blvd Street Improvements – Castro Valley
Client:  County of Alameda
Description of Work: Reconstruct of existing street, sidewalk repairs, sewer, water, and storm drains.
Value:  $8,906,835.65
Work Completed:

 

#03-1F4804- HWY 5 Near Woodland- Woodland
Client:  CalTrans
Description of Work: Asphalt overlay of existing highway.
Value:  $6,453,759.00
Work Completed:

 

Sanitary Sewer Mainline Bottlenecks – Livermore
Client:  City of Livermore
Description of Work: Rehabilitation of existing sanitary sewer system.
Value:  $2,002,480.00
Work Completed:

 

2010 ARRA Cost Savings Overlay Project – Sonoma County
Client:  County of Sonoma DPW
Description of Work: Asphalt overlay on various country roads.
Value:  $2,298,957.00
Work Completed:

 

San Marco Unit #8 – Pittsburg
Client:  A.D. Seeno Construction
Description of Work: Site development for new subdivision, including earthwork, finegrade rock and pave, sewer, water and storm drains.
Value:  $3,466,767
Work Completed:

 

Berryman Reservoir Replacement- Berkeley
Client:  EBMUD
Description of Work: Demolition of existing 2.1 million gallon reservoir and construction of new development.
Value:  $6,012,000.00
Work Completed:

 

#04-0A18U4- HWY 101 at the Cotati Grade in Sonoma County
Client:  CalTrans
Description of Work: Realign and improve sight distance on highway. Cast-in-place concrete retaining walls and bridges. MSE walls, asphalt paving and concrete barriers.
Value:  $48,756,304.00
Work Completed:

 

#I580/ Isabel Avenue Interchange, Contract #1 – Livermore
Client:  CalTrans
Description of Work: Realign and improve sight distance on highway. Cast-in-place concrete retaining walls and bridges. MSE walls, asphalt paving and concrete barriers.
Value:  $17,775,000
Work Completed:

 

Highway 580/101 Separation – San Rafael
Client:  CalTrans, Department of Transportation
Project Photos
Description of Work:
Value:  $9,350,000
Work Completed:


Cal Park Hill Tunnel Multi-Use Pathway – San Rafael
Client: County of Marin
Project Photos 
Description of Work:
Value:  $5,400,000
Work Completed:


Highway 280 – San Mateo County
Client: CalTrans District 4
Project Photos
Description of Work:
Value:  $19,333,000
Work Completed:


Highway 101/12 – Santa Rosa
Client: Department of Transportation/MCM Construction
Project Photos
Description of Work:
Value:  $17,860,000
Work Completed:


Floodwall Improvements – Hayward
Client: Alameda County Flood Control & Water District
Project Photos
Description of Work:
Value:  $4,630,000
Work Completed:


Highway 84 – Alameda County
Client: CalTrans, Department of Transportation
Project Photos 
Description of Work:
Value:  $2,275,000
Work Completed:


Geyserville Stabilization Project – Geyserville
Client: CalTrans, Department of Transportation
Project Photos 
Description of Work:
Value:  $4,300,000
Work Completed:


Highway 580 – Livermore
Client: CalTrans, Department of Transportation
Project Photos 
Description of Work:
Value:  $30,500,000
Work Completed:


Interstate 80/North Texas Street Interchange – Fairfield
Client:  City of Fairfield
Project Photos 
Description of Work:
Value:  $19,5000.00
Work Completed:


Highway 12 – Fairfield
Client: CalTrans, Department of Transportation
Project Photos 
Description of Work:
Value:  $6,000,000
Work Completed: