*LOW BIDDER*

Ghilotti Construction was low bidder on 3 new projects in the past few weeks. Way to go estimating! 

City of Davis – Surface Water Pipeline Project

GCC – $17,971,660.00

41,855 total LF of new waterline, Bore and jack pipe under Union Pacific Railroad and Hwy 80, 10,000 tons of asphalt paving

City of Santa Rosa – Long Drive and Vicinity Sewer and Water Improvements

GCC- $2,222,218.00

3,000 tons of asphalt paving, concrete curb / gutter / sidewalk,  3,100 LF of sanitary sewer mains, 1,200 LF of water mains)

2015 Road Rehabilitation Southern Region

GCC – $1,614,373.00

6,500 tons of asphalt paving in Mill Valley

Leave a Reply